Week #4 (June 28-July 5, 2007)
McFadden Hall looks much different than it did just four weeks ago when demolition started. A total of twelve bricked up window frames have been restored to their original size on the South and East sides of the building. The interior of the building is still undergoing environmental abatement. Floor and ceiling tiles have been removed in several areas of the building during this process. Multiple dumpsters of rubble have already been removed. The demolition crew has recycled as much of the contents as possible throughout this entire project.
Next week we plan to share current interior photos of McFadden Hall.